Student Sports and Amenity Precinct

Tuesday, 5 December, 2023

We are pleased to share an important update regarding Phase 1 of the UCD Student Sports and Amenity Precinct Project which is a significant milestone in the ongoing development of student sports and amenities on the UCD Belfield Campus. Key facilities and infrastructure to be delivered as part of this phase of works include:

  • UEFA standard 3G artificial soccer pitch
  • Half hockey training pitch
  • Hurling wall
  • Six artificial five-a-side soccer pitches
  • New road and access routes

For further details into the long-term vision of the Sports and Student Amenity Project, please visit the Sports and Amenity Project Page

Project Updates

The next phase of works for the Student and Sport Amenity Project has commenced.

Please note that from Wednesday 10th April for a period of several months a diversion will be in place on the pedestrian & cycle route from the UCD Nexus/Beech Hill Gate at Founders District (Belfield Office Park) running alongside the current construction zone, UCD Bowl and ending at the rear of the National Hockey Stadium to allow works taking place in this area to proceed.

The primary diversion will be in place via the National Hockey Stadium & Sports Centre, 5 a-side soccer pitches and Newstead.

 Wayfinding signage will be in place throughout the diversion route via the National Hockey Stadium & Sports Centre in both directions to guide users. For this phase of works vehicular access on the campus ring road alongside the construction zones will be maintained at all times. To view a map of the diversion coming into effect please (opens in a new window)click here.

Update No. 1: Phase 1 Commencement of Works

Kilwex Ltd have been appointed as the main contractor for this Phase of the project. Works are now commencing with completion expected in early 2025. An outline of the works area is shown on the (opens in a new window)Site Set-Up Map. Works for the remainder of 2023 will focus primarily on site preparatory works as outlined below.

Immediate Six-Week Focus:

  • Site Preparations: Site boundary fencing including tree protective fencing to be erected. Setting up site compound area.
  • Site Clearance: site clearance and exploratory excavations, along with commencing some utility installation works outside the existing roadways.
  • Pedestrian Pathway Construction: A new footpath will be constructed adjacent to the Athletics track up to the Nexus pedestrian gate, maintaining campus connectivity as the works progress in 2023.
  • Pedestrian Diversion Route: A pedestrian diversion route will be established to link to the entrance to the Athletics Track. Please see details of this diverted route on the (opens in a new window)Athletics Track Pedestrian Diversion Map.

Wayfinding signage will be put in place by the contractor in advance to alert users of any diversions to access routes as the works progress.

Appreciation is extended to all campus users for the support and understanding as the project progresses.